ESR1

Annie Ringvall-Moberg: ESR-1

Institution: CERN

Nationality: Swedish

annie.julia.ringvall-moberg@cern.ch

The ISOLDE facility at CERN is used to produce radioactive isotopes by bombarding a target made out of e.g. uranium carbide with protons. Each target is prior to being installed at the on-line facility tested at an off-line facility, which is a small independent isotope separator. As of today, ISOLDE has only one off-line facility which essentially is occupied by target testing. A second off-line system, Offline 2, consisting of an ion source, a mass separator and an RFQ cooler, is currently under construction. Offline 2 will mainly be used for developments of ion sources and for development of beam manipulation methods using the RFQ cooler. The RFQ cooler, which essentially is a copy of an RFQ installed at the on-line facility, makes it possible to improve energy spread and divergence of the ion beam emitted from the ion source.

My primary task will be to take part in the construction and commissioning of the new isotope separator, along with its RFQ cooler. Furthermore, I will investigate laser induced molecular break-up processes at ISOLDE.

Post no.

ESR 1

Duration

36 months

Work package

WP3, D3.2: Molecular break-up by laser in RFQ cooler

Recruiting partner

CERN, Switzerland

Objective

Construction and commissioning of a mass separator and RFQ-Cooler for molecular isotope beams break-up.

Expected results

  1. Participate in the construction of an isotope separator
  2. Commission an isotope separator with beam
  3. Proceed with the assembly of a RFQ cooler
  4. Commission a RFQ cooler with beam
  5. Participate in molecular break-up tests

Enrolment for PhD at

University of Manchester, United Kingdom

Planned secondment(s)

Lemer Pax, France – 5 months –Engineering design for a maintenance-free RFQ cooler/purification device